Council scheduled to consider revised WSDOT agreement for 88th St NE Phase 1 federal funds

Ahead of the June 8, 2026 meeting, the Marysville City Council was scheduled to consider authorizing the Mayor to sign and execute a revised Local Agency Agreement Supplement No. 2 and a Local Agency Federal Aid Project Prospectus with WSDOT to obligate construction funds for the 88th St NE Corridor Improvement — Phase 1 project 1.

What the records say

In the June 8, 2026 agenda packet, the council was scheduled to consider a motion authorizing the Mayor to sign and execute Local Agency Agreement Supplement No. 2 and a Local Agency Federal Aid Project Prospectus with the Washington State Department of Transportation for the 88th St NE Corridor Improvement — Phase 1 project 1. The packet says the council had approved an earlier LAA Supplement No. 2 and prospectus on April 13, 2026 to obligate $4,407,274 in federal construction funds, but WSDOT had not executed that agreement because of right-of-way certification and design approval processing requirements 1. The packet also says the Puget Sound Regional Council has since approved an additional $1,712,777, increasing the total federal construction obligation to $6,120,051, and that the changes require a revised LAA Supplement and corresponding prospectus 1. Once WSDOT executes the agreement, the project will be advertised for construction, according to the packet 1. The available records do not establish the meeting's outcome.

  • The council was scheduled to consider authorizing the Mayor to sign and execute Local Agency Agreement Supplement No. 2 and a Local Agency Federal Aid Project Prospectus with WSDOT for the 88th St NE Corridor Improvement — Phase 1 project.
  • The packet says the earlier April 13, 2026 agreement to obligate $4,407,274 in federal funds had not been executed by WSDOT, and PSRC later approved an additional $1,712,777, raising the total federal construction obligation to $6,120,051.
  • The packet says the project will be advertised for construction once WSDOT executes the agreement.

Why it matters

The June 8 item concerns the agreement needed before the 88th St NE Corridor Improvement — Phase 1 project can be advertised for construction, according to the packet 1. The packet identifies $6,120,051 in total federal construction obligation for the project after the additional PSRC funding 1. The available records do not establish whether the council approved the motion.

What changed / what's next

  • The packet says the proposed June 8 action follows a revised LAA Supplement and prospectus needed after PSRC increased the federal construction obligation from $4,407,274 to $6,120,051 and after WSDOT had not executed the earlier agreement 1.
  • The available records do not establish the meeting's outcome; whether the council approved the motion is not shown in the supplied packet 1.