Pavement preservation contract award was scheduled for June 8 meeting
Materials for the June 8, 2026 City Council meeting listed a recommended motion to award a $4,550,000 pavement preservation contract to Reece Construction Company — an amount above the program's allocated budget 1.
What the records say
Materials for the June 8, 2026 Marysville City Council Regular Meeting listed a recommended motion for the 2026 Pavement Preservation Project under Review Bids. The motion would authorize the Mayor to sign and execute a contract with Reece Construction Company for $4,550,000.00 and approve a 10% management reserve of $455,000.00, for a total allocation of $5,005,000.00 1. The agenda bill states bids were opened May 28, 2026, with seven bids received and Reece Construction Company the apparent low bidder; the engineer's estimate was $5,125,000.00 1. The bill also states the contract amount exceeds the allocated budget for the 2026 Pavement Preservation Program and that a future budget amendment funded through the Transportation Benefit District will be necessary to cover the overage 1. The available records do not establish the meeting's outcome 1.
- The agenda listed a recommended motion to authorize the Mayor to sign and execute the 2026 Pavement Preservation Project contract with Reece Construction Company 1.
- The contract amount listed was $4,550,000.00, with a $455,000.00 (10%) management reserve, for a total allocation of $5,005,000.00 1.
- Bids were opened May 28, 2026; the City received seven bids and Reece Construction Company was the apparent low bidder, below the $5,125,000.00 engineer's estimate 1.
- The agenda bill states the amount exceeds the allocated budget for the 2026 Pavement Preservation Program and a future budget amendment funded through TBD will be necessary 1.
- The planned work includes 2-inch grind and overlay, ADA curb ramp upgrades, sidewalk infill on 5th St, and shoulder widening on 100th St 1.
- The available records do not establish the meeting's outcome 1.
Why it matters
The proposed total allocation is $5,005,000.00, and the agenda bill states this exceeds the program's allocated budget, meaning a future budget amendment funded through the TBD would be needed if the award proceeds 1. Pavement preservation work affects road conditions across the city, including 2-inch grind and overlay, ADA curb ramp upgrades, sidewalk infill on 5th St, and shoulder widening on 100th St 1. The available pre-meeting records do not establish whether the Council approved the motion 1.
What changed / what's next
- The June 8, 2026 City Council agenda listed a recommended motion to award the 2026 Pavement Preservation Project contract to Reece Construction Company for $4,550,000.00 with a $455,000.00 management reserve, totaling $5,005,000.00 — an amount the agenda bill says exceeds the program's allocated budget 1.
- The available records do not establish whether the Council approved the contract award 1.
- If the motion were approved, the next step described is the Mayor signing and executing the contract 1.
- A future budget amendment funded through TBD would be needed to cover the overage above the program's allocated budget 1.